ERCES Installation: Bringing the Design to Life

Professional ERCES installation requires expertise and attention to detail. Learn about the installation process, best practices, and what to expect.

ERCES installation transforms your approved design into a working system. Professional installation is critical—improper installation can result in failed inspections, inadequate coverage, and costly rework.

Installation Overview

A typical ERCES installation includes:

  1. Donor antenna installation on the roof
  2. BDA (Bi-Directional Amplifier) installation in equipment room
  3. Cable routing throughout the building
  4. Distribution antenna installation on each floor
  5. Power and monitoring connections
  6. System optimization and testing

Pre-Installation Requirements

Before Installation Begins

Ensure the following are complete:

  • AHJ design approval received
  • Building permits obtained
  • Frequency coordination documented
  • Equipment ordered and received
  • Installation contractor selected
  • Building access coordinated
  • Other trades coordinated (electrical, fire alarm)

Site Readiness

The building should have:

  • Dedicated electrical circuit for BDA equipment
  • Equipment room space with proper ventilation
  • Roof access for donor antenna installation
  • Cable pathway access (risers, conduits, ceiling space)
  • Fire alarm interface ready (if required)

Donor Antenna Installation

Location Selection

The donor antenna should be positioned to:

  • Have clear line-of-sight to public safety towers
  • Minimize cable run to BDA
  • Be accessible for maintenance
  • Be protected from physical damage

Installation Requirements

RequirementSpecification
MountingRated for wind/ice loads
GroundingPer NEC and manufacturer
WeatherproofingAll connections sealed
Lightning protectionAppropriate arrestors
Cable routingProtected from damage

Common Donor Antenna Types

  • Yagi antennas for directional coverage
  • Omnidirectional antennas for multiple tower directions
  • Panel antennas for specific directional needs

BDA Installation

Location Requirements

BDAs should be installed in:

  • Climate-controlled spaces (0-50°C operating range)
  • Areas with adequate ventilation
  • Accessible locations for maintenance
  • Protected from physical damage
  • Near electrical service

Installation Best Practices

Mounting:

  • Secure wall or rack mounting
  • Adequate clearance for airflow
  • Accessible for service

Electrical:

  • Dedicated circuit as specified
  • Proper grounding and bonding
  • Surge protection

Connections:

  • Proper connector installation
  • Cable strain relief
  • Labeled connections

Cable Installation

Cable Types

Cable TypeApplicationFire Rating
Coaxial (plenum)Distribution runsCMP rated
Coaxial (riser)Vertical runsCMR rated
Fire-ratedSurvivability areas2-hour rated
Hybrid fiberLong runsPer application

Routing Considerations

Pathway Survivability:

  • Follow NFPA 1221 requirements
  • Use fire-rated pathways where required
  • Maintain proper firestopping

Signal Quality:

  • Minimize cable lengths
  • Avoid sharp bends
  • Maintain separation from interference sources
  • Use appropriate connectors

Installation Standards

  • Maximum bend radius per manufacturer
  • Proper support intervals
  • Labeled at both ends
  • Tested after installation

Distribution Antenna Installation

Antenna Placement

Distribution antennas are placed based on:

  • Design coverage calculations
  • Building construction materials
  • Ceiling height and type
  • Aesthetic requirements

Common Antenna Types

Ceiling-mount omnidirectional:

  • Most common for office areas
  • 360-degree coverage pattern
  • Typically mounted above ceiling tiles

Wall-mount directional:

  • For corridors and specific areas
  • Focused coverage pattern
  • Visible mounting

Public safety DAS antennas:

  • Purpose-built for ERCES
  • Appropriate frequency coverage
  • UL listed components

Installation Requirements

  • Secure mounting per manufacturer
  • Proper connector installation
  • Antenna orientation per design
  • Accessible for testing and maintenance

Power and Monitoring

Power Requirements

ERCES systems require:

Primary Power:

  • Dedicated circuit(s)
  • Appropriate amperage
  • Surge protection

Backup Power:

  • Battery backup (typically 12-24 hours)
  • Proper battery installation
  • Charging system

Monitoring Connections

Connect to building systems:

  • Fire alarm panel (supervisory)
  • Building management system (optional)
  • Remote monitoring (if required)

Quality Control During Installation

Inspection Points

PhaseInspection Items
Rough-inCable routing, pathway protection
EquipmentBDA mounting, connections
AntennasPlacement, mounting, connections
FinalComplete system, labeling

Documentation During Installation

Maintain records of:

  • Equipment serial numbers and locations
  • Cable routing and lengths
  • Test results at each phase
  • Any deviations from design
  • Photos of concealed work

Common Installation Challenges

Challenge: Existing building infrastructure limitations Solution: Coordinate with building management, plan alternative routes

Challenge: Construction schedule conflicts Solution: Early coordination with general contractor

Challenge: Signal interference from other systems Solution: Identify sources, adjust antenna placement or add filtering

Challenge: Aesthetics concerns in finished spaces Solution: Use appropriate antenna types, coordinate placement

Working with Installers

Contractor Qualifications

Look for installers with:

  • ERCES-specific experience
  • Knowledge of local AHJ requirements
  • Proper licensing and insurance
  • Manufacturer certifications
  • References from similar projects

Installation Timeline

Typical installation duration:

Building SizeDuration
Small (under 50,000 sf)1-2 weeks
Medium (50,000-200,000 sf)2-4 weeks
Large (over 200,000 sf)4-8+ weeks

Factors affecting timeline: building complexity, access restrictions, coordination requirements.

Next Steps

After installation is complete:

  1. Contractor performs initial system testing
  2. Address any coverage issues
  3. Prepare for commissioning
  4. Schedule AHJ inspection

Ready to install your ERCES system? Connect with qualified installers who have experience with your building type.