4 Step 4 of 5

ERCES Commissioning: Verifying System Performance and Compliance

Commissioning verifies your ERCES system meets all requirements before final approval. Learn about the commissioning process and AHJ inspection.

Commissioning is the final verification phase before your ERCES system receives official approval. This process confirms that the installed system meets design specifications, code requirements, and provides the coverage necessary for emergency responder communication.

What is ERCES Commissioning?

Commissioning includes:

  • Acceptance testing to verify coverage
  • System functional testing of all components
  • Documentation review and compilation
  • AHJ inspection and approval
  • Final certification of the system

Pre-Commissioning Checklist

Before requesting commissioning, verify:

Installation Complete

  • All antennas installed per design
  • BDA equipment operational
  • All cables terminated and tested
  • Backup batteries installed and charged
  • Monitoring connections complete
  • System labels in place

Documentation Ready

  • As-built drawings updated
  • Equipment cut sheets compiled
  • UL listings documented
  • Frequency coordination letters
  • Contractor certifications

Initial Testing Complete

  • Contractor has verified coverage
  • Signal levels meet requirements
  • All components functional
  • Issues identified and resolved

Acceptance Testing

Coverage Verification

Test the system against IFC 510 requirements:

Critical Areas (99% coverage required):

AreaTest Requirement
Fire command centerAll locations
Exit stairwaysEvery landing
Elevator lobbiesEach floor
Standpipe locationsEach location
Fire pump roomMultiple points

General Areas (90% coverage required):

AreaTest Methodology
Office floorsGrid testing (50-100 ft)
Parking structuresGrid testing
Common areasRepresentative points
CorridorsLinear testing

Signal Level Requirements

Minimum signal levels (typical):

MeasurementRequirement
Inbound (downlink)-95 dBm or better
Outbound (uplink)-100 dBm or better
DAQ (voice quality)3.0 or better

Test Documentation

Acceptance test reports must include:

  • Test methodology description
  • Equipment used (calibrated)
  • Test point locations on floor plans
  • Signal measurements at each point
  • Pass/fail determination
  • Technician qualifications

Functional Testing

BDA Testing

Verify amplifier operation:

  • Normal operation indicators
  • Gain settings correct
  • All frequency bands operational
  • Alarm conditions reported properly
  • Remote monitoring functional (if applicable)

Backup Power Testing

Test battery backup system:

TestRequirement
Battery capacity12-24 hours (per code)
Transfer timeSeamless switchover
Low battery alarmProper indication
Charger operationCorrect charging

Monitoring System Testing

Verify supervisory connections:

  • Power failure indication
  • Battery trouble indication
  • Component failure indication
  • Signal to fire alarm panel (if required)

AHJ Inspection

Scheduling the Inspection

Contact your AHJ to:

  1. Request inspection appointment
  2. Confirm required documentation
  3. Understand inspection process
  4. Identify who should attend

What Inspectors Review

Documentation Review:

  • Approved design drawings
  • As-built documentation
  • Test reports
  • Equipment listings
  • Frequency coordination

Physical Inspection:

  • Equipment installation
  • Antenna locations
  • Cable routing and protection
  • Labeling and identification
  • Backup power installation

Functional Demonstration:

  • System operation
  • Signal coverage (spot checks)
  • Monitoring functionality
  • Backup power operation

Common Inspection Issues

IssueResolution
Coverage gapsAdd antennas, adjust system
Documentation incompleteProvide missing documents
Installation deficienciesCorrect per inspector notes
Labeling missingAdd required labels
Monitoring not connectedComplete connections

Final Approval and Certification

Approval Documentation

Upon successful inspection:

  • AHJ issues approval letter or certificate
  • System is certified for occupancy requirements
  • Annual testing schedule established
  • Maintenance requirements documented

Certification Requirements

Maintain records of:

  • AHJ approval documentation
  • Acceptance test reports
  • As-built drawings
  • Equipment information
  • Maintenance schedule

Post-Commissioning Requirements

Immediate Actions

After approval:

  1. File all documentation
  2. Provide building management with system information
  3. Establish maintenance contract
  4. Schedule first annual test
  5. Train building personnel on system basics

Ongoing Requirements

Commissioning Timeline

Typical commissioning duration:

ActivityDuration
Pre-commissioning prep1-2 days
Acceptance testing1-3 days
Documentation compilation1-2 days
AHJ inspection scheduling1-3 weeks
AHJ inspection1 day
Issue resolution (if needed)Varies
Final approval1-2 weeks

Working with Your Commissioning Team

Key Participants

  • ERCES contractor/installer
  • Testing technician
  • Building representative
  • Fire alarm contractor (if integrated)
  • AHJ inspector

Coordination Requirements

Ensure all parties understand:

  • Commissioning schedule
  • Documentation requirements
  • Access requirements
  • Roles and responsibilities

Next Steps

After successful commissioning:

  1. Implement ongoing maintenance program
  2. Train building staff on system basics
  3. Maintain documentation for inspections
  4. Schedule annual compliance testing

Need help with ERCES commissioning? Connect with experienced professionals who can guide you through the approval process.

Ready for ERCES Commissioning?

Connect with qualified ERCES professionals who can help.

Schedule Commissioning